INFORMATION

Project Name:

K104 Kenton Road, SR8 to Chestnut Grove Road

Project Limits:

The project is located on Kenton Road from Forrest Avenue (SR8) to Chestnut Grove Road (K158) in Dover, Kent County.

Project Need:

The goal of this project is to improve traffic safety and operations and to enhance bicycle and pedestrian accessibility along Kenton Road between SR8 (Forrest Avenue) and Chestnut Grove Road.

Project Overview:

The proposed improvements include:

  • 11' Travel Lanes and 5' Shoulders/Bike Lanes
  • 10' Shared-Use Path on East side of Roadway from SR8 to YMCA
  • 5' Sidewalks
  • Curb and Gutter
  • Right and Left Lanes at all intersections with Bike lane
  • Additional Traffic Signals at Greentree Drive and Chestnut Grove Road
  • Potential Double Left Turn Lanes from Walker Road and College Road onto Kenton Road
  • Potential two southbound through travel lanes from SR8 to College Road

Public Workshop

A public workshop was held on October 24, 2016 at Dover High School.

Current Schedule

  • Survey Plans – April 2016
  • Alternatives Workshop – October 2016
  • Refine Alternatives – December 2016
  • Preferred Alternative Workshop – Fall 2017